Bolo AI Agent·Laguna Texas Resources
Back to Portfolio

OAKMONT A UNIT

4 wellsGlasscock County, TXWolfcamp A + L SpraberryVintage: NewActive

Last updated: May 17, 2026

Operating Snapshot
Current Production
11,508 bbl/mo
30-day avg · peak 36,080
SCADA
Variance to Analog
−22%
vs Wolfcamp A analog
Type Curve Model
Deferred Production
~430 BOEPD avg
driven by M2H/M3H shut-in
Deferred BOE Model
Next Risk Window
OVERTON B ~Jun 15
completion within 1,800 ft
Drilling Schedule
Bolo Recommendation

Recommended Intervention Sequence

  1. 1
    M3H ESP retrofit + restart
    Lowest-risk rate restoration. Gas-handler ESP with controlled restart.
    4–6 weeks · ~$385K illustrative capex
  2. 2
    M2H MIT + BHP survey
    Confirm mechanical integrity and reservoir pressure before restart decision.
    2–3 weeks
  3. 3
    M2H restart / workover if mechanically clean
    Controlled restart with gas-handling mitigation.
    Gated on Step 2 results
  4. 4
    Protection protocol before OVERTON B completion
    Water cushion + shut-in window + offset-pressure monitoring.
    Pre-Jun 15
  5. 5
    Defer protection-refrac decision
    Only revisit after workover outcome and OVERTON B behavior are known.
    Deferred

Bolo prioritizes lowest-capital, fastest-rate-recovery action first. Higher-capital refrac decision is deferred until diagnostics confirm need.

Why Bolo recommends this
3

M2H rate-decline event aligns with PANTHER E frac window

Critical

SCADA shows casing-pressure climb and field notes record failed ESP restarts; frac interference is the leading hypothesis, but mechanical and reservoir alternatives remain open.

SCADAField NotesOffset Frac ScheduleLift Telemetry

Next action: BHP survey + MIT before any restart or refrac decision.

M3H restart attempts are gas-locking

High

Field notes show repeated restart failures under higher-GOR conditions; gas-handler retrofit is the lowest-risk first intervention.

Field NotesLift TelemetryGOR Trend

Next action: Approve ESP gas-handler retrofit and restart plan.

OVERTON B completion creates near-term protection window

Critical

Planned completion within 1,800 ft creates parent-child risk for remaining producers.

Drilling ScheduleSpacing MapOffset Protection Procedure

Next action: Load water cushion 5–7 days pre-stim and assign offset monitor.

Field Notes
47 this asset
May 18, 2025·M2H

"Tried M2H restart again. Won't catch. Pump amperage flatlining. Calling it — leaving shut in."

restart failedESPshut in
Apr 22, 2026·M3H

"M3H gas locking on restart this morning. Pulled equipment for review. Same pattern as M2H."

gas lockrestart failedM3H
Apr 9, 2025·M2H

"Second restart attempt M2H — gas locking under depleted draw. Casing pressure still climbing overnight."

gas lockpressure anomalyM2H
Apr 8, 2025·M2H

"M2H casing pressure up overnight. Tried restart. ESP gas locking, unstable drawdown."

gas lockrestart failedpressure anomaly
Evidence Preview
Pressure & Rate — M2H

Casing pressure climbs as oil rate collapses; restart attempts coincide with field-note markers.

Production vs Type Curve

Cube tracks ~22% under Wolfcamp A analog; divergence widens after PANTHER E completion.

Open Interventions
4 of 8
PriorityItemOwnerStageNext action
CriticalM3H ESP retrofit + restartLift Eng.ValidatedSubmit AFE
CriticalM2H MITWellworkScheduledMobilize crew
HighM2H BHP shut-in surveyReservoirValidatedSequence after MIT
HighOAKMONT A water-cushion preloadCompletionsScreeningConfirm OVERTON B date