Bolo AI Agent·Laguna Texas Resources
Laguna Texas Resources

Portfolio Dashboard

31 horizontal unit assets · 41 wells · 4 counties · plus FOSTER-PEGUES vertical waterflood · Updated May 17, 2026

Field Production vs Plan
5,480BOEPD
-5% vs 5,800 BOEPD 2026 plan
−320 BOEPD vs plan, widening
RRCPlan
Deferred Production
540BOEPD avg
16.2 MBOE deferred over last 30d · 38% lift · 31% facility · 22% reservoir/offset-frac · 9% other
Up from 290 BOEPD avg last 30d
SCADAField Notes
Wells Below Type Curve
12of 41
vs Wolfcamp / Dean analog
Was 8 last month
Type Curve Model
Well Intervention Queue
14items
4 critical · 3 aging > 60d · funnel: 7 screening · 4 validated · 2 approved · 1 executing
1 new item this week
Intervention Ledger
LOE per BOE (30d)
$9.40/BOE
30-day trailing
+$0.40 vs prior 30d
LOS Variance
Daily Field Brief · J. Rincón· Glasscock area
Today · 6:52 AM · 4 min

Tried restart on M2H again — gas-locked within 20 minutes. Casing pressure 2,420, higher than yesterday. M3H still down, Williams crew pulled ESP, found about 200 feet of sand fill above the pump intake.

·

OVERTON B — NexTier rolled in last night, frac spread set, stage one starts Sunday morning.

9 wells touched · 3 vendors on site · 1 issue flagged
Pattern: "gas-locking" 4× in 14 days (M2H, M3H, COZART A 1)
Assets Needing Attention

Ordered by severity. Click any asset for full deep-dive.

Reservoir = rock + wellbore signals (pressure, water cut, GOR, frac hit, integrity, type-curve variance) · Operational = lift, intervention queue, workovers, AFE status, field actions

OAKMONT A UNIT

(Glasscock)
4 wells · Wolfcamp A + Lower Spraberry cube · 2024
Reservoir: CriticalOperational: Concern

M2H and M3H both shut in with failed ESP restarts. Rate-decline events align with offset PANTHER E completion (Apr 2025). Cube running 22% below Wolfcamp A analog. OVERTON B completion within 1,800 ft on ~Jun 15 — protection protocol pending.

~430 BOEPD deferred (30d avg) · 3 open interventions · 1 critical · Next milestone: OVERTON B ~Jun 15
Frac-hit signatureESP gas-lockOffset completion riskProtection protocol pending
Sequence: M3H workover → M2H MIT/BHP → OAKMONT A water-cushion preload pre-OVERTON B
Open asset

BIG BEND UNIT

(Glasscock)
1 well · Spraberry · 2021
Reservoir: CriticalOperational: Concern

Production halted Oct 2021 after only 4 months at high rate. Root cause never closed. Last reported pre-halt issue: pumping pressure climbing. Stranded asset 4+ years — MIT recommended.

Carrying cost ~$45K/yr · MIT cost ~$120K · P&A cost ~$280K if abandoned
Stranded assetMIT requiredP&A candidatePressure anomaly pre-halt
Schedule MIT · Pull wellbore log · Investigate vs P&A decision memo
Open asset

CROCKETT

(Borden)
1 well · Spraberry · 2019
Reservoir: ConcernOperational: Watch

30,214 bbl cumulative in 80 months — bottom decile vs basin analogs. Year-2 decline 71% suggests under-stimulated original completion. Mechanically intact.

~95 BOEPD below analog · Refrac evaluation in screening · Pre-refrac BHP test needed
Under-stimulatedRefrac screeningMechanically intact
Run Chan plot pre-refrac · Confirm BHP via shut-in test
Open asset

Field Production Trends

Field-level production and GOR trends across Glasscock, Borden, Dawson and Ector areas. Vertical waterflood (FOSTER-PEGUES) excluded.

County Summary

30-day rolling operational performance by county

CountyAssetsWellsBOEPDvs PlanDeferred BOELOE/BOEOpen Int.Status
Horizontal Assets
Glasscock11151,960 bbl/d-14%280$10.206 (2 critical)
Concern6 open · plan gap -14%
Borden10131,150 bbl/d-9%130$8.804 (1 critical)
WatchTrending below plan
Dawson791,170 bbl/d-3%80$9.103 (1 critical)
WatchTrending below plan
Ector341,200 bbl/d+2%50$9.401
GoodAll assets on track
Horizontal subtotal31415,480 bbl/d−5%540$9.4014 (4 crit.)
WatchField underperforming plan
Vertical Waterflood
Foster-Pegues122270 bbl/d$13.203 (1 crit.)
ConcernWaterflood under review
Portfolio total32635,750 bbl/d−5%540$9.5517 (5 crit.)
WatchPortfolio below plan